Look and feel of the visual schedule

The graphical part of the schedule

The graphical part - the diagram - is one of the three main areas in your schedule and is positioned in the middle of the view

The diagram shows you which machine center is working on which production order routing line/operation and when.

    The elements of the graphical part in detail

    Bars

    Each production order routing line/operation of a production order is represented by a bar that is either colored or white. The colored area of a bar indicates that this timespan is during the work time of the underlying machine center. The white area of a bar indicates that this timespan is during the non-work time of the underlying machine center (also see below "Calendar". The bar color depends on the selected color scheme (see below). 

    The following information can be gathered from optical indicators:

    • Currently marked operation
      An orange frame indicates a selected operation

     

    VPS_Currently_Marked_Operation-1

    • The operation changed but not saved yet
      A gray dot appears at the end of the operation bar

      VPS_Operation_Changed_but_not_Saved
    •  Violated due date
      A red dot appears at the end of the operation bar

    Operation_Violation_Due_Date

    • Violated routing links
      A warning sign on the operation bar indicates violated routing links


    • Operations potentially scheduled outside the visible time range
      In addition to being indicated by a warning symbol, these operations get moved to the standby resource.



    • Pinned operations, production order lines, production orders
      The context menu allows you to pin the above elements so that they can't be moved.

    VAPS - pin complete


    The different options are visually indicated as follows:
      • Pin without consuming capacity

      • Pin consuming capacity

      • Link violation after having pinned an element. The picture below shows that the predecessor of a pinned operation was moved behind this operation

    • Setup times

      The setup times can be visualized as a light grey section at the beginning of the bar.  

      You can switch between showing or hiding the setup times by a menu item:

      VAPS-setup-times-menu

      The color representing the setup time can be easily specified in the VAPS color settings:

    VAPS-color-setup-setup-times2

    • Display mode for overlapping operations

    Usually, overlapping operations are shown in an "optimized" way, meaning that the resource row with the respective operations gets extended in height so that the operations are completely visible. Since the VAPS schedules with finite capacity, overlapping operations are avoided, and hence this is a rare case.

    However, some customers have contacted us with the following use case: They need to create operations with a length of zero to define a common starting point for parallel routings without blocking capacity. These operations will then be scheduled at the first possible position which will result in a very high stacked resource. For these cases, we added two new context menu items so that users can now decide whether overlapping operations are to be shown overlapped in one row or stacked. 

    The picture below illustrates the different display modes:

    • Info symbol indicates additional information on the routing line

      In Business Central, users can add additional information to a production order routing line by creating comments, tool information, personnel information, and quality measure information that are used, e.g., for describing certain specialties that need to be followed during the production process. As this is, of course, valuable information, the VAPS now helps the planner to quickly recognize whether a production order line has such a comment so that the special requirements are not overlooked.

      VAPS - comment symbol on operation

      To activate this feature, tick the according option in the "General" settings of the VAPS setup dialog:

      VAPS show info symbol

      • Shortcut to creating additional information

    As of release 1.16 of the VAPS, you can directly create and edit this information by clicking the according item in the context menu.

    vaps-create-additional-information

    Earliest Start Date

    The VAPS comes with the convenient automatic scheduling functions "Add all", "Fill idle times", "Apply routing," and "Tighten operations". These functions can be limited to only schedule production order routing lines/operations so that they start at or later than the date defined. This is done by the field "Earliest Start Date" that has been implemented on production order, production order line, and production order routing line level. Clicking an operation with an earliest start date will display an according date line. 

    vaps - earliest start date

    If the earliest start date is defined on all levels, the latest available date will be used for scheduling and if the "Consider EMAD" option is activated, this date will also be taken into account, meaning that the latest of all four dates will be considered.

    Operations with an earliest start date can nevertheless still be dragged manually to an earlier start.

    The earliest start date can also be calculated automatically. For details on this functionality, please click here.

    Calendar

    The grey and white area in the background visualizes the work and non-work periods of the respective work/machine center. They are derived from the respective shift calendars.

    • Show/hide non-woking periods

    Some planning situations require to focus on the working periods of a work or machine center only. You can choose to hide or show the common non-working period by activating a menu item of the same name.

    vaps-show-hide non-working-times

      • Handling of standby resources
        Currently, the calendar of the related work center is applied to standby resources, so that when the non-working period is hidden, the non-working periods that are shared by all calendars will not be displayed and the timescale will collapse during these periods.
        On the other hand, switching the non-working periods on means that those periods that are common to all calendars will be displayed.

    • Individual design of weekend colors and date line grids
      Some of our customers use a 24-hour working calendar and, as they told us, sometimes have difficulties navigating and planning by day in the diagram area because the change between the days and/or weekends and working periods are not clearly visible. This, in turn, forces the planner to constantly look back and forth between the timescale and the plan. So we set to work and implemented three new visual elements to create a better connection between the timescale and diagram area:

      • vertical separation lines between individually selectable intervals

      • individual background and bar  colors, and transparency degree for weekends

      • an individual background color and transparency degree for the standby resource

    In the picture below, the date line grid mode is set to "Daily", the background color for the weekend to a light blue, and the Standby color to a slightly darker yellow with a high degree of transparency:

    VAPS - set standby and weekend color

    The according settings can be found in the "Appearance" area of the VAPS setup dialog.

    Progress

    If you want to always be informed about the progress of your production order routing lines of released production orders, you can do this by displaying a progress bar below the production order routing line. You can decide whether the progress is calculated based on the posted quantity consumption or on the production time passed.

    VAPS - select progress calculation

    The color of the progress bar depends on the routing status and the percentage of completion:

    • Status finished: black

             VAPS - progress bar finished

    • Status “none,” “planned,” “in progress”:

      • Progress by quantity / by time < 100% : grey

        VAPS_progress_bar_grey
      • Progress by quantity / by time > 100 % : red
        VAPS_progress_bar_red

    When attempting to move operations that are "in progress," a warning message appears, prompting whether scheduling should proceed with the original quantity or with the current remaining quantity. In the latter case, the input quantity will change, with a warning to the user that this action may result in misleading progress bar information.

    VAPS - warning moving operations in progress

    Links

    Predecessor/successor relations are shown as arrows ("links") between the bars. They are only shown for the production order that is currently selected.
    • links between operations of one production order
    VPS_Links_Between_Operations
    • links between operations of different production orders if they are linked to each other by reservations (make to order) OR links between production order lines coming from one production order (make to stock)


    Work date

    A red vertical line in the chart indicates the work date, this usually being the current date.

    Required due date

    The required due date is a specific VAPS field, that you can set on the "Production Order" card:

    This date can only be set and changed by the user. We recommend to set this date in case you have hard due dates for one or more specific production orders.

    The tooltip

    The tooltip of the VAPS provides further details about an operation and is customizable.

    VAPS customize tooltip

    The "Standby" resource

    The standby resource does not exist in your Dynamics 365 Business Central machine centers. It is a virtual machine center that we automatically create in every work center. It contains all production order routing lines/operations that are not yet scheduled from within the VAPS, and hence are just scheduled by the Business Central scheduling run. The standby resource gets highlighted by a yellow background (and an infitiy symbol next to its name in the table part):


    Please note that
    • the standby resource always is treated as a resource with infinite capacity
    • all other machine centers are treated as finite capacity resources (with a capacity of 1)

    View color modes

    VAPS - color modes

    It is possible to stress different aspects of your plan with the VAPS by using different views where you define certain colors for the bars depending on the things you want to highlight. This feature can help you to tackle specific challenges and answer certain questions. The links provided will lead you to a detailed explanation of each respective view.

    Item View

    Machine/Work Center View

    Production Order View

    Production Order Status View

    Progress View

    Shop Floor Status View

    Availability View

    Wait Times View

    MRP View

    Production Line Assignment View

    Production Line Sequence View