Working with the schedule in the VJS

Create links

The VJS enables creating links between all levels of your plan

A context menu allows to create all sorts of links: between jobs, job tasks and job planning lines, even between differetn levels, e.g., job to job planning line and job task to job.

According to your needs and planning situation, you can select between two possible relations:

  • Start-Start (the successor must not start before the predecessor)
  • Finish-Start

VJS_create_link


The link structure you build this way, will be taken into account, when one element – job, job planning line etc. - in this chain gets moved.

VJS_move_linked_jpl

Schedule successors

This option that can be found in the menu ribbon ensures that the link structure is taken into account with no buffer time, i.e. linked operations are processed without temporal offset. This applies for the selected node and all its successors. 

VJS_schedule_successors

Violated link orders appear in red

If the link order within a link structure gets violated, the according link(s) appear in red.

VJS_violated_link_order